2020 Canyon Gym Renovation

After an incredible 3 year fundraising campaign, the Canyon High School Foundation, Canyon faculty, staff, students, families, boosters, alumni, local businesses and the community have proven you are Committed to the C!

Thank you to the 558 donors who contributed a total of $300,000 in individual and corporate donations, and Orange Unified School District for partnering with the Canyon High School Foundation to complete the funding of this $1.29M project.

From September 2020 through January 2021 (estimated completion date to come), the Canyon gym will receive a new BOSE sound system, bleachers, wooden floor, paint and ADA compliant bathroom upgrades.

Week 1 Progress

Demo of the Canyon Gym started 1 week ago and the progress is amazing. Thank you to OUSD and all of our donors for making this possible.

Week 4 Transformation

We are a month into the Canyon gym renovation and things are moving right along. The floorboards have arrived and must temper inside the gym for 2 weeks prior to installation.

Week 5 Progress

It's week 5 and things are moving along with the Canyon Gym Renovation! Changes can be seen on the outside with a fresh coat of paint. Thank you to all who made this possible, you are appreciated.

Week 8 Transformation

What a difference 8 weeks makes! The floorboards have been tempered, sub-floor installed and flooring laid. In addition, the interior got a fresh coat of paint - check out that ceiling!

Week 10 Progress

Check out the amazing progress in just 10 short weeks on the Canyon Gym. Thanks to everyone that was "Committed to the C" and made this dream a reality.